If six men can do a piece of work in 14 days. how many are needed to complete the project in 21 days

Respuesta :

Davidfridman
Davidfridman Davidfridman
  • 12-01-2018
you would need 9 poeple
Answer Link

Otras preguntas

An atlas is a book of statistical data. Please select the best answer from the choices provided T F
The Baroque composer famous during his lifetime for dramatic pieces like operas and oratorios was
What is proper etiquette for starting a football game? A. Coin toss, with the home team calling heads or tails. Winner gets to choose either to have his team
Supporters of the Union side in the Civil War generally supported what political party? Democratic Party Republican Party Whig Party None of the above
What does adherent mean?
What is the relationship between the digit 9 in 79,401
Which of the following is NOT a characteristic of members of the Plant Kingdom? Plants are multicellular All plants are eukaryotic Plants are heterotrophs Plant
What is a chromosome
The Vedas are sacred texts read by Buddhists. a. True b. False
If a person attempts to make a phone call while they are waiting for a meeting to begin, they are _______. a. Combining tasks b. Multitasking c. Sequential t